400 Ton & 150 Ton Quenching Overhead Cranes Exported to Vietnam: For a Heat Treatment Production Line

Summary: Weihua delivered two double girder quenching overhead cranes, 400 tons and 150 tons, to a heat treatment manufacturer in Vietnam. The 400-ton unit is reported to be the largest-capacity quenching crane in the country. Both cranes work on the same production line.

Aperçu du projet

ObjetDétails
DestinationVietnam
ClientHeat treatment manufacturer
EquipmentDouble girder quenching overhead cranes
Quantité2 sets
Crane 1400(200+200)+20t
Crane 2150/30+20t
ApplicationHeavy workpiece quenching and handling
Duty classA7
ContrôlePLC centralized control; stator voltage speed regulation on main hoist
Delivery2026

Both cranes are installed and in service. Together they handle heavy workpieces through the full quenching sequence, from furnace to quench medium.

How a Quenching Crane Works

A quenching crane moves a hot workpiece from the furnace into the quench medium, usually water, brine or oil. The typical sequence is:

  1. The crane picks up the heated workpiece at the furnace.
  2. It transfers the load to the quench station.
  3. It lowers the workpiece into the medium within a short, controlled time.
  4. After the set holding time, it lifts the workpiece out and moves it to tempering or cooling.

Speed, timing and load stability decide the quality of the result. A slow or swinging entry can cause uneven structure or surface damage. This is why a quenching crane is a special-duty machine and not a standard overhead crane.

Challenges on This Project

  • Constant heat radiation. The furnace area exposes cranes to heat that can age cables and destabilize signals.
  • Two cranes in one bay. Their combined heat output adds to the load on electrical components.
  • Mixed loads. Heavy and light loads need different speeds, with frequent starts and stops.

Weihua’s Solution

Heat protection

  • High-temperature-resistant cables on both cranes.
  • A temperature-controlled electrical room inside the main girder.
  • A double-layer insulated operator cab.

These measures keep heat away from core electrical and control components. They target the typical high-temperature faults, such as cable ageing and unstable signals, so the cranes can run long continuous shifts.

PLC-coordinated dual-hook control

Both cranes use a latest-generation PLC centralized control system. The main hoist uses stator voltage speed regulation, so the system can coordinate the acceleration and deceleration curves of the main and auxiliary hooks. This gives:

  • fast lifting under heavy load and stable movement under light load;
  • smooth handling through frequent starts, stops and load changes;
  • less workpiece swing, which helps avoid uneven structure and impact damage.

Crane configurations

 400 Ton Crane150 Ton Crane
Marking400(200+200)+20t150/30+20t
Levage principalTwo 200 t hoisting units150 t main hoist
Other hoists20 t hoist30 t and 20 t units
StructureBox-type double girder with walkways and access stairsBox-type double girder with walkways and access stairs

Hoist roles follow the markings on the girders. Final configuration details are confirmed in the project design.

Typical parameters for this crane class

ParamètresTypical Range
La portée28 m
Hauteur de levage25 m
Obligation de travailA7

What to Consider When Choosing a Quenching Crane

  • Workpiece weight and hook layout. Match the main and auxiliary hoists to your load range.
  • Furnace temperature and radiant heat. This decides cable, electrical room and cab protection.
  • Quench medium. Water, brine and oil bring different safety and speed demands.
  • Lowering speed and control accuracy. Timing affects the quality of the workpiece.
  • Span, lifting height and duty class. These follow your building and production rhythm.

Quote

“Quenching leaves little room for error. We designed these cranes around heat protection and coordinated hook control, so the customer’s line can run steadily with heavy workpieces.”
— Weihua Group, Overseas Business Division

FAQ

What is a quenching overhead crane?
It is a special-duty overhead crane that moves hot workpieces from a furnace into a quench medium on a controlled schedule.

Why does a quenching crane need heat protection?
Furnace radiation can age cables and disturb signals. Heat-resistant cables, an insulated electrical room and a cab reduce these risks.

Can one crane lift 400 tons with two 200-ton hoists?
A 400(200+200)t marking means two 200-ton hoisting units form the 400-ton main lift. The exact lifting method follows the crane’s design and rated load table.

What information is needed for a quotation?
Workpiece weight, furnace temperature, quench medium, span, lifting height and duty class.

Need a Quenching Overhead Crane?

Send us your requirements and our engineers will propose a configuration.

→ Pont roulant de trempe pour une aciérie
→ Pont roulant à double pont
→ Request a Quote

→ WEIHUA vous invite à VINAMAC EXPO 2026 à Hô Chi Minh-Ville – Visitez le stand B310

Crane Specialist

Lily

Senior Crane Specialist / Technical Advisor

Online Support

Over 10 years of experience in overhead & jib crane solutions. Dedicated to helping global clients find the most efficient and cost-effective lifting equipment.